During the discussions surrounding the PUD’s recently passed 2019 budget, General Manager Larry Dunbar stated the goal to heighten focus on improving the customer experience, crew safety, and overall system reliability.

Recent near system-wide transmission outages have led the PUD to survey its transmission corridor for potential tree hazards. Trees are the PUD’s number one cause of outages.

The 30 – 45-year-old aging electric distribution infrastructure also fails from time-to-time resulting in an outage. During the last six weeks the PUD has experienced three faults in the underground cable along Swansonville Road which serves as the primary feeder for power to Port Ludlow. These faults have led to the repeated loss of power for thousands of customers in the Port Ludlow area. In 2016 and 2017 only one fault occurred. The underground cable is approximately 9,000 lineal feet. It is the original cable and is at the end of its service life.

To improve system reliability, the PUD recently finished the installation of a new conduit system for the first 2,700 lineal feet along Swansonville Road. Beginning Saturday December 15th, the PUD will begin installing about 600 feet of cable into the new conduit, including the section where the most recent faults occurred. PUD crews may be closing one lane of Swansonville Road which could extend into next week. Flaggers will be on site. PUD staff are continuing to evaluate the cost and timeline to complete the remainder of the project and will present the findings to the Board of Commissioners in the new year.

You can continue to keep up-to-date by visiting the PUD website at www.jeffpud.org

Russ Michel
PLVC Utilities Chair